Asset register for built assets
An asset register is a schedule of components that form part of a built asset such as a building. It may form part of a building owner's manual, (operation and maintenance manual or O&M manual) for a building which contains all the information required for the operation, maintenance, decommissioning and demolition of a building.
An asset register may be prepared for every component in a building, or just for the ‘active’ assets that require regular inspection, maintenance, cleaning or replacement, such as building services components.
Ideally, it should be prepared during the design stage, but it may be prepared during construction, or as part of a survey of a completed building. Software is available to help prepare and manage asset registers, and companies exist that will carry out an asset survey to compile an initial register.
An asset register may contain a wide range of information, such as:
- A description of the asset.
- Identification number.
- Location.
- Size.
- Access information.
- Supplier.
- Installer.
- Purchase price.
- Date of acquisition.
- Purchase order number.
- Date of delivery .
- Ownership records.
- Current value.
- Condition and defects.
- Maintenance requirements and intervals.
- Information about spares.
- Photographs.
- Drawing references.
- Running cost.
- Energy performance.
- Certification.
- Health and safety information.
- Service level agreements.
- Warranties.
- Disposal date.
- Method of disposal.
- Sale price.
An asset register can be useful for programming and providing the information necessary to carry out activities such as inspections, cleaning and planned preventative maintenance as well as for carrying out repairs or alterations. In addition, it can be useful for budgeting purposes, or for valuing assets, and a copy might be archived as part of an annual financial reporting process.
Asset registers will tend to be prepared digitally, will be searchable and include links to supporting documentation. They may be integrated with maintenance scheduling software, computer-aided facilities management (CAFM) software or building information models (BIM).
Increasingly, building information models (or asset information models) should include all the of information that previously might have been held on a separate asset register. An asset information model (AIM) is an operational BIM model that compiles the data and information necessary to support asset management, that is, it provides all the data and information related to, or required for the operation of an asset. The information required for an asset information model should be defined in the asset information requirements (AIR). In the case of a new asset, asset information requirements will have been used to develop the employer’s information requirements (EIR) incorporated into the tender documentation for a project.
Once compiled, it is very important that the asset register is kept up to date. Responsibility for maintaining the asset register may be given to an asset manager.
NB NRM3: Order of cost estimating and cost planning for building maintenance works, defines an asset register as: '...a record of applicable maintainable assets, including information such as constructed specification, operational performance data, financial and technical details about each asset.'
See also: Creating an asset register for construction projects.
[edit] Related articles on Designing Buildings
- Asset information model
- Asset information requirements.
- BIM and facilities management.
- BIM.
- Building owners manual.
- Contract register.
- Construction Operations Building Information Exchange (COBie).
- Creating an asset register for construction projects.
- Employers Information Requirements.
- NRM3.
- Service level agreement.
- Site records and registers.
- Types of register
Featured articles and news
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.